Project Budget:

  • $7.11 Million Project Cost

Funding:

  • Bond Measure S (Ex. B. #60)

Schedule:

  • Design (Commenced): 04/2005
  • Completed as of 04/2006: $700,000 of improvements
  • Construction Completed: 06/2014
vc_ii1.jpg
 
vc_ii2.jpg

Project Objectives & Notable Features:

  • Storm and sanitary sewers
  • Electrical systems
  • Water and irrigation
  • Natural gas systems
  • Signage