Project Budgets:

  • 26,657 Gross Square Feet
  • 18,638 Net Square Feet
  • 33,858 Square Feet Site Development
  • $21.247 Million Project Costs

Funding:

  • Bond Measure S (Ex. B #34): $21.247 Million

Schedule:

  • Schematics: 08/2006 (Completed)
  • Design Development: 06/2007 (Completed)
  • Construction Documents: 12/2007 (Completed)
  • DSA Review: 05/2008 (Completed)
  • Bid/Award: 06/2008 - 07/2008 (Completed)
  • Construction: 08/2008 - 11/2010 (Completed)

Architect:

  • MVE Institutional

Contractor:

  • Woodcliff Corporation
oc_paa1.jpg

Project Objectives & Notable Features:

  • 400-seat multipurpose auditorium;
  • 100-seat black-box theater;
  • Oxnard College Television Studio, pre-production and post-production facilities;
  • Site area set aside for the expansion of the auditorium stage, costume and carpentry shops, additional storage, etc., if program development warrants.

Implementation Strategy: