Square Footage:

Parking Structure: 194,310

Police Station: 5,331

Total Square Feet: 199,641

Project Budgets:

  • $12.0 Million construction budget

Funding:

  • Bond Measure S (Ex. B #19)

Schedule:

  • Design: 08/2010 (Completed)
  • DSA Review: 07/2012 (Completed)
  • Bid Date: 09/06/2012 (Completed)
  • Award Date: 06/2010 (Completed)
  • Construction: 07/2014  (Completed)

Architect:

  • International Parking Design

Bid Documents:

mc_parking_structure1.jpg

Project Objectives & Notable Features:

The project  to relieve the shortage of campus parking.