Project Budgets:

  • 40,079 Gross Square Feet
  • 14,551 Net Square Feet
  • $5.8 Million Project Costs

Funding:

  • Bond Measure S (Ex. B #5): $6.9 Million

Schedule:

Library Renovation:

  • Design: 04/2004 - 4/2005 (Completed)
  • DSA Review: 04/2005 - 09/2005 (Completed)
  • Bid/Award:  01/2006 - 04/2006 (Completed)
  • Construction: 05/2006 - 07/2007 (Completed)

        Architect:  Carde Ten


First Stop:

  • Design: 08/2012 (Completed)
  • DSA Review: 03/2013-07/2013 (Completed)
  • Bid/Award: 07/2013-08/2013 (Completed)
  • Construction: 08/15/2013  (Completed)

        Architect: Amador Whittle Architects

mc_lr1.jpg
 
mc_lr2.jpg
mc_lr3.jpg

Project Objectives & Notable Features:

Library Renovation:

The existing library will be renovated to provide 17 additional classrooms that will facilitate the removal of 15 existing portable classrooms scattered throughout the campus.

Additional existing Library space will also be renovated to provide for a student Independent Learning Center with associated support space.

Existing utility systems, particularly mechanical and data/telecommunications will be upgraded to provide a contemporary learning environment. 

First Stop:

Facilities will be renovated to facilitate most all student functions from Registration to Student Loans/Scholarships and Finance.