Project Budget: Athletics Field
- $3.2 Million Project Costs
Project Budget: Gymnasium Renovation
- $3.7 Million Project Costs
Funding:
- Bond Measure S (Ex. B #16)
Schedule: Athletics Field:
- Design: 02/2004 (Completed)
- Bid/Award: 03/2004 (Completed)
- Construction: 03/2005 (Completed)
Architect:
Schedule: Gymnasium Bleachers:
- Design: 05/2005 - 02/2006 (Completed)
- DSA Review: 02/2006 - 07/2007 (Completed)
- Bid/Award: 08/2006 - 11/2006 (Completed)
- Construction: 07/2006 - 08/2007 (Completed)
Architect:
Schedule: Gymnasium Renovations:
- Design: In Planning
- DSA Review: --
- Bid/Award: --
- Construction: --
Architect:
|
|