Project Budget: Athletics Field

  • $3.2 Million Project Costs

Project Budget: Gymnasium Renovation

  • $3.7 Million Project Costs

Funding:

  • Bond Measure S (Ex. B #16)

Schedule: Athletics Field:

  • Design: 02/2004 (Completed)
  • Bid/Award: 03/2004 (Completed)
  • Construction: 03/2005 (Completed)

Architect:

  • Gonzalez/Goodale

Schedule: Gymnasium Bleachers:

  • Design: 05/2005 - 02/2006 (Completed)
  • DSA Review: 02/2006 - 07/2007 (Completed)
  • Bid/Award: 08/2006 - 11/2006  (Completed)
  • Construction: 07/2006 - 08/2007 (Completed)

Architect:

  • Albert & Rachlin

Schedule: Gymnasium Renovations:

  • Design: In Planning
  • DSA Review: --
  • Bid/Award: --
  • Construction: --

Architect:

  • TBD