Architect Rendering

Project Budget:

  • $6 million project budget

Funding:

  • Bond Measure S

Schedule (phased project):

  • First Phase Bid Award:  June 25, 2013
  • First Phase Construction: March 10, 2015 (Completed)
  • Last Phase of Construction (to be completed):  Summer 2017

Architect:

  • Anderson Kulwiec Appleby (Dave Anderson)

Project Objectives and Notable Features:

This phased project to renovate the Maintenance and Operations facilities includes demolition of old buildings, construction of new grounds buildings,equipment building, administration building, new and renovated shop buildings,new parking lot, trash areas, and pedestrian walkway.