Project Budget: $7.11 Million Project Cost Funding: Bond Measure S (Ex. B. #60) Schedule: Design (Commenced): 04/2005 Completed as of 04/2006: $700,000 of improvements Construction Completed: 06/2014 Project Objectives & Notable Features: Storm and sanitary sewers Electrical systems Water and irrigation Natural gas systems Signage