Project Budget:

  • 36,300 Building Gross Square Feet
  • $8.51 Million Project Budget

Funding:

  • Bond Measure S (Ex. B #47): $5.51 Million

Schedule:

  • Design: 01/2008 (Completed)
  • Bid/Award: 12/2009 (Completed)
  • Construction: 08/2011 (Completed)

Architect:

  • David Bury & Co.
vc_app_s_dp2.jpg

Project Objectives & Notable Features:

  • Provide Americans with Disabilities upgrades and fire, life safety, and HVAC code upgrades. Current welding and machine shops are without fire suppression systems.
  • Increase and improve lab and storage space for the growing Auto Tech program.
  • Modernize existing classrooms and class labs.
  • Improve the exterior finishes and building system.