Project Budgets:
- 33,000 Building Gross Square Feet
- $15.44 Million Project Budget
Funding:
- Bond Measure S (Ex. B #43): $22.476 Million
Schedule:
- Design: 06/2008 (Completed)
- Bid/Award: 12/2009 (Completed)
- Construction (to be completed): 06/2012 (Completed)
Architect:
|
|