Project Budget:
- 18,600 building gross square feet
- $15 million project budget
Funding:
- Bond Measure S
Schedule:
- Bid Award: August 28, 2013
- Construction (to be completed): July 2015 (COMPLETE)
Architect:
- Gensler
Project Objectives and Notable Features:
The Applied Science Center is a state-of-the art single story building that will house a Visualization Classroom, Career Training Center, two large lecture halls (120 and 200 seats), administrative offices, lobby/circulation space, restrooms and storage areas.