Project Budgets:

  • 47,240 Gross Square Feet
  • 29,045 Net Square Feet
  • 62,000 Square Feet Site Development
  • $24.65 Million Project Costs

Funding:

  • Bond Measure S (Ex. B #7): $24.65 Million

Current Schedule:

  • Schematic: (Completed)
  • Design Development: (Completed)
  • Construction Documents: 05/2006 - 11/2006 (Completed)
  • DSA Review: 12/2006 - 06/2007 (Completed)
  • Bid/Award: 07/2007 - 10/2007 (Completed)
  • Construction: 01/2008 - 05/2010 (Completed)

Architect:

  • Gensler
mc_aca_ctr1.jpg
 
mc_aca_ctr2.jpg

Project Description:

  • 20 classrooms: capable of seating 50 students;
  • 13 classrooms: capable of seating 35 students;
  • 2 classroom spaces: capable of expanding to accept seating of 80-100 students;
  • Staff offices, conference room, storage and support facilities.